Arrived at 3 pm on Monday for the first inspection with the project boss. Explained to us about all the different wires and hoses. There are even special lines for termite control. He was also able to answer many of our questions and we are quite pleased at the quality of the work. The wall board is to be started tomorrow and he gave Bob permission to insulate the walls in the garage.

The house looks more complete with the windows and doors in.
Here is the garage with the stack of wall board waiting to be put on.

So our dear friend Bud came with all of his equipment. The sun is shining and off came the jackets to start the insulating. They had about 2 hours of daylight left to do it.


Bud did most of the stapling and Bob measured, cut and put in the bats of insulation.



Even the little areas over the garage door got filled. The job was finished in the 2 hours even with the cleanup and putting away of all the equipment etc. Then off we went to the city market for dinner. A job well done..